TOPEKA — Kansas utility regulators handed a win Tuesday to landowners concerned about a transmission line bisecting large swaths of prairie grassland in the state’s south-central region.

The Kansas Corporation Commission voted unanimously to approve part of Evergy’s proposed construction of a 133-mile transmission line. But the three-member commission stopped short of allowing the line to cross U.S. Highway 77 east into the Flint Hills, saying Evergy must reconsider that portion of the line.

“The …