A group of Maryland landowners aggrieved by land surveys for a proposed 67-mile electricity transmission line across northern Maryland are petitioning the U.S. Supreme Court to take up their case.

In their request, filed with the nation’s highest court Wednesday, 60 petitioners dispute lower court rulings that allowed surveyors from power line company PSEG Renewable Transmission to enter onto their properties for field studies for the Maryland Piedmont Reliability Project.

The landowners are