Less than 24 hours after Vineyard Wind secured a win in federal court that lifted the project suspension, it sailed its 62nd and final turbine tower out of the Port of New Bedford on a brutally cold Wednesday morning. The shipment comes more than two years after the first turbine went out, capping off a long installation process that hit several unexpected bumps and delays along the way.

All that remains now …